! Keywords: Crashing / Forecasting / Product Management / Production / Project Evaluation & Review Technique / Scheduling / Uncertainty / Steel Industry / Construction Industry;
MIN 5 C1 + 6 C2 + 4 C3 + 2 C4 + 3 C5 + 9 C6 - 5 PCRASH
SUBJECT TO
2) C1 + EF1 >= 9
3) C2 + EF2 >= 7
4) C3 - EF1 + EF3 >= 5
5) C4 - EF1 + EF4 >= 8
6) C4 - EF2 + EF4 >= 8
7) C5 - EF3 + EF5 >= 6
8) C6 - EF4 + EF6 >= 9
9) C6 - EF5 + EF6 >= 9
10) EF6 + PCRASH = 29
END
SUB C1 4.00000
SUB C2 4.00000
SUB C3 2.00000
SUB C4 4.00000
SUB C5 3.00000
SUB C6 4.00000
|