! Keywords: Break Even Point / Inventory / Marketing / Product Management / Product Mix / Production / Sales;
! Maximize revenue minus costs;
MAX 3 A + 3 B + 3 C + 3 D + 2 D2 + 3 E + 2 E2
- 4 M1 - 4 M2 - 3 M3
SUBJECT TO
! Machine time used = machine time made available;
2) 12 A + 7 B + 8 C + 10 D + 10 D2
+ 7 E + 7 E2 - 60 M1 = 0
3) 8 A + 9 B + 4 C + 11E + 11 E2 - 60 M2 = 0
4) 5 A + 10 B + 7 C + 3 D + 3 D2
+ 2 E + 2 E2 - 60 M3 = 0
! Product limits;
5) D <= 20
6) E <= 20
! Machine availability;
7) M1 <= 128
8) M2 <= 128
9) M3 <= 128
END
|